After you sign: what happens next

Signing feels like the finish line, but it’s the start of a process that usually takes weeks to months. Here is each step from site survey to switch-on, what you need to do at each one, and what to check before you make each payment.

The short answer

After you sign, the installer does a detailed site survey, finalizes the design, gets building permits and applies to your utility to connect. Installation itself often takes one to three days, followed by a local inspection and the utility’s permission to operate. From signing to switch-on often takes about one to three months, and longer where permits or utilities are slow. Don’t turn the system on until the utility gives written permission.

The steps at a glance

Every installer and every town does things a little differently, but the order is usually the same. Most of the time between signing and switch-on is paperwork, not roof work.

StepWhat happensTypical timeYour part
1. Cooling-off and paperworkContract and any financing are finalized.First few daysRead everything. Note any cancellation deadline.
2. Site surveyA technician measures the roof, attic and electrical panel.Within a week or twoGive access, point out any roof issues.
3. Final designThe engineer sets the layout and equipment.About 1 to 2 weeksCheck that it matches your contract.
4. Permits and approvalsBuilding permit, HOA approval and the utility’s connection application.A few weeks to a few monthsSign forms, answer HOA questions.
5. InstallationRacking, panels, inverter and wiring go in.Often 1 to 3 daysClear the driveway and access areas.
6. InspectionThe local building department checks the work.Days to a few weeksBe home if the inspector needs access.
7. Permission to operateThe utility approves and may swap your meter.Days to several weeksWait for the written go-ahead.
8. Monitoring and first billsThe system runs and you watch the numbers.First yearCompare production with the estimate.

These times are common ranges, not promises. Permit offices, HOAs and utilities set their own pace, and backlogs come and go. Check your state briefing for notes on your state’s utility rules. This page is part of our session on how to read an installer quote.

The first few days: cooling-off and paperwork

If you signed at home, the FTC’s Cooling-Off Rule generally gives you until midnight of the third business day to cancel sales of $25 or more, and the seller must give you a cancellation form. Saturdays count as business days. Your contract or state law may give you more time.

Use these days well, even if you’re happy with your choice:

  • Read the full contract and any loan, lease or PPA documents, not just the summary page.
  • Check the numbers against your final quote: price, system size, equipment models, deposit and payment schedule.
  • Confirm what was promised out loud is in writing. If not, ask for an addendum now.
  • Save copies of everything in one folder, paper or digital. You’ll need these documents for 20 years or more.

If something doesn’t match, raise it before the cancellation window closes. See door-to-door solar sales for how to cancel, and solar contract terms to check for what to look for.

Site survey and final design

Your quote was probably designed from satellite images and your bills. The site survey checks the real details. A technician usually spends an hour or two at your home and may:

  • Measure roof faces, angles and obstructions like vents and chimneys.
  • Go into the attic to check the rafters and roof deck.
  • Take shade readings at different points on the roof.
  • Look at your main electrical panel and meter, and photograph labels and ratings.

The engineer then finalizes the design. Sometimes this changes things. A rafter problem can move panels, more shade can drop a panel or two, and a full electrical panel can mean an upgrade.

If the final design changes the system size, equipment or price, you should get a written change order to approve. Don’t let changes happen by phone.

Check the final design against your contract. A drop from 8 kW to 7.2 kW at the same price raises your price per watt from $3.00 to about $3.33 and cuts production by about 10%. That’s worth a conversation. See what is a solar change order.

Permits, HOA and the utility application

This is the step that most often causes waiting. Your installer usually handles all of it, but it helps to know what’s going on.

  • Building and electrical permits from your city or county confirm the design meets local building, fire and electrical codes.
  • HOA approval, if you have a homeowners association. Many states limit how far an HOA can restrict solar, but you may still need to submit plans.
  • The interconnection application asks your utility for permission to connect a system that can send power to the grid. The utility checks the design and your local grid.

Ask your installer for updates at each stage, and ask for copies of the approved permit and the utility’s approval for your records. If your project sits for weeks with no news, a polite email asking what’s pending is reasonable.

The interconnection application is also where your utility’s export rules get locked in. Depending on your state, the rules in place when your application is approved may decide how you’re credited for extra power for years. If your state is changing its net metering rules, ask your installer when your application will be filed and which rules it will fall under. In California, for example, systems moved to net billing (NEM 3.0) in April 2023, with average export credits around 4¢ a kWh, so the timing of applications mattered a great deal. See our net metering session for how these rules work.

Payments often fall due around this point. If your contract ties a payment to permit approval or equipment delivery, ask for proof that the milestone has happened before you pay.

Making the waiting weeks easier

The gap between signing and install day can feel long, and silence can make you wonder whether anything is happening. A few simple habits keep you informed without turning you into a full-time project manager.

  1. Ask for one contact person. A named project coordinator, with an email address, is better than a general sales line.
  2. Agree on updates. Ask how often you’ll hear from them, for example every two weeks or at each milestone.
  3. Keep a short log. Write down the date of each step, each payment and each conversation. It takes seconds and settles most later questions.
  4. Prepare your home. Trim branches that touch the roof, clear the path to your electrical panel and attic hatch, and tell your neighbors if a crane or large truck will block the street.
  5. Tell your insurer. Ask your homeowner’s insurance company whether the system needs to be added to your policy. Some policies cover it automatically, and some need a change.
  6. Plan around the roof. If you’ve been putting off a small roof repair, ask the installer whether it should happen before the panels go up.

If you feel the project has stalled, ask a direct question in writing: what step are we on, what is it waiting for, and when do you expect it to move? A good installer can answer all three. If the answer is that a permit or utility approval is pending, that’s usually normal. If no one can say what’s pending, it’s time to ask more firmly.

And if you’re still at the quote stage while reading this, these steps are worth asking about up front. See questions to ask a solar installer for the process questions to add to your list.

Installation day, inspection and permission to operate

Installation

For a typical roof-mounted system, the crew is often on site for one to three days. A battery, a main panel upgrade or a complex roof can add time. Expect ladders, noise and a short power shutoff while the electrician connects the system. Clear the driveway and move cars, and make sure the crew can reach your electrical panel and attic.

Before the crew leaves, walk around with the lead installer. Ask to see where the inverter and disconnect switches are, how the monitoring works and what each label means. Take photos of the finished work, including the attic under the attachment points if you can.

Inspection

The local building department inspects the system to confirm it was built to code and matches the permit. If something is flagged, the installer fixes it and schedules a re-inspection. This is the installer’s job and shouldn’t cost you extra.

Permission to operate

After the inspection, the utility gives written permission to operate (often shortened to PTO). It may swap your meter for one that measures power in both directions. Don’t turn the system on until you have PTO. Running it early can break your utility agreement, and you may not be credited for power you send back.

This is a good moment to make the final payment, if your contract ties it to inspection or PTO. Ask for lien waivers (signed releases from the installer and any major suppliers) with the final payment, so no one can place a lien on your home later.

Your first months: monitoring and bills

Once the system is running, two habits will tell you whether it’s working as promised.

Watch the monitoring

Check your monitoring app weekly for the first month and monthly after that. Look for days with zero production on sunny days, a single panel making much less than the rest, or alerts you don’t understand. Report problems to the installer in writing. A monitoring app that shows each panel makes this much easier.

Read your new bills

Your bill will look different. It may show power you used, power you sent back and credits carried forward. Many utilities settle credits once a year (a true-up), so one month doesn’t tell the full story. Your bill will usually still include a monthly connection charge.

Example: checking your first year

  • Standard example home: 8 kW system, estimate of about 10,400 kWh a year
  • Average month: 10,400 / 12 = about 870 kWh, with more in summer and less in winter
  • Home uses 1,100 kWh a month, or 13,200 kWh a year
  • Share of use covered: 10,400 / 13,200 = about 79%
  • Expected yearly savings: about $1,660 at 16¢ a kWh with full retail net metering

After 12 months, total production within about 5% to 10% of 10,400 kWh is usually reasonable. A shortfall of 15% or more is worth raising with the installer.

This is an example. Weather varies from year to year, and production depends on your location, roof and shading. Panels typically lose about 0.5% of output a year. Use your own estimate from your contract.

If production comes in well short, check whether your contract includes a production guarantee. See what if my system produces less than promised.

Paperwork to keep, and when things go wrong

Keep one folder with everything. You’ll need it for warranty claims, for selling your home and for any problem with your utility or lender.

  • The signed contract, change orders and any addenda.
  • Loan, lease or PPA documents and payment records.
  • Equipment model numbers, serial numbers and warranty documents for panels, inverter and any battery.
  • The workmanship warranty and the installer’s service contact.
  • The approved permit, final inspection record and the utility’s permission to operate.
  • Lien waivers and receipts for every payment.
  • Photos of the finished system and the attic.

If something goes wrong, such as long delays, a roof leak or a failed part, contact the installer in writing first, with dates and photos. Most problems are resolved this way. If not, check your contract’s dispute process, then contact your state contractor board or attorney general. If your installer has closed, see what happens if your solar company goes out of business, and contact the equipment makers directly for product warranty claims.

When the after-signing stage hurts the payback

  • Change orders add thousands to the price after signing, such as an unplanned panel upgrade or roof repair.
  • Months of permit or utility delays push back your first year of savings while loan payments may already have started.
  • The final design is smaller than the quote but the price stays the same.
  • The system runs before permission to operate and you lose credits for power sent to the grid.
  • Production problems go unnoticed for months because no one checks the monitoring.

In the standard example home, each $1,660 of extra cost or lost savings adds about a year to a simple payback of about 14.4 years.

Key takeaways

  • Most of the time between signing and switch-on is permits and utility approval. Installation itself often takes one to three days.
  • Use the first few days to check the contract against your quote, while any cancellation right still applies.
  • Approve any design or price change through a written change order.
  • Never turn the system on before the utility’s written permission to operate, and ask for lien waivers with the final payment.
  • Watch your monitoring and compare 12 months of production with the estimate in your contract.

Questions people also ask

Do loan payments start before my system is turned on?

Sometimes. Some solar loans start interest or payments when the installer is paid or the system is installed, not when the utility gives permission to operate. Check your loan documents for the start date and ask the lender directly. If long delays are likely in your area, ask whether the first payment can be tied to switch-on instead.

Can I cancel after the site survey if the design changes?

It depends on your contract. Many solar contracts let you cancel if the final design differs a lot from the proposal, or if the system can’t be permitted, often with a deposit refund. Others charge a fee. Read the cancellation and change order clauses, and ask the installer in writing what your options are before approving a revised design.

Why is my first solar bill higher than I expected?

A few things can cause it. Your utility may not have applied net metering yet, the bill may cover days before permission to operate, or credits may be held until a yearly true-up. Winter months also produce less. Look at the kWh sent to the grid on your bill, and call your utility if credits seem missing after the first full cycle.