What is a solar change order?

Sometimes the system you signed for isn’t quite the system that gets built. A change order is how that difference is written down and approved. Here is when they happen, what a fair one looks like, and how to respond.

The short answer

A solar change order is a written change to your contract after you’ve signed, usually to the system size, equipment, layout or price. They often follow the site survey or engineering review, for example when fewer panels fit than planned or your electrical panel needs an upgrade. A fair change order explains what changed and why, shows the new price and production estimate, and needs your signature before work goes ahead.

Why change orders happen

Many quotes are drawn up from satellite images and your utility bills. After you sign, the installer sends someone to measure your roof, check the attic and look at your electrical panel (the site survey), and an engineer reviews the design. That’s when surprises show up. Common reasons for a change order include:

  • Fewer panels fit than the satellite design showed, because of vents, roof setbacks required by fire codes, or roof condition.
  • Your electrical panel needs an upgrade to handle the solar connection. See whether you need a new electrical panel.
  • The roof needs structural work or repairs before panels can go on.
  • Equipment substitution, when the quoted panel or inverter isn’t available and the installer proposes another model.
  • Permit or utility requirements that add equipment, such as an extra disconnect switch.
  • You asked for a change, such as adding a battery or more panels.

Some of these are honest discoveries that no one could have seen from a satellite image. Others should have been caught earlier. Either way, the change belongs in writing.

Change orders aren’t unique to solar. Builders, roofers and remodelers use them all the time. What makes them matter in solar is that a small change to size or equipment ripples through everything else: the price per watt, the production estimate, the savings and the payback. A change that looks minor on paper can move your numbers by more than you’d expect.

What a fair change order shows

A good change order reads like a mini contract. It should state:

  • What’s changing, in plain terms, and why.
  • The new system size, panel count and equipment models.
  • The new total price, and the change in price.
  • The new first-year production estimate.
  • Any change to the timeline.
  • A place for you to sign and date, with a copy for you.

It’s worth working out the new price per watt and checking how the change affects your savings. Here’s how that might look if a design shrinks.

Example: fewer panels than planned

  • Original contract: 8 kW for $24,000 ($3.00 per watt), about 10,400 kWh a year
  • Change order: 7.2 kW for $22,400, about 9,360 kWh a year
  • New price per watt: about $3.11
  • Savings at 16¢ per kWh with full retail net metering: about $1,498 a year, down from about $1,664

Simple payback: about 15.0 years, up from about 14.4 years

Example figures for the standard home. The price fell, but not in step with the size, so each watt costs more. That’s a fair thing to question.

Some costs really are fixed, such as design, permits and the crew’s trip, so it’s normal for the price to fall a little less than the size. But if the price barely moves while the system shrinks a lot, ask the installer to show how they reached the new figure.

How to respond to a change order

  1. Don’t sign on the spot. Ask for the change order by email and give yourself a day or two.
  2. Ask for the reason in writing, with photos or the engineer’s notes if the change came from the site survey.
  3. Check the math. Work out the new price per watt and the new production estimate, and compare them with your other quotes.
  4. Ask about alternatives. If a panel upgrade is needed, ask whether a smaller system or a different connection method could avoid it. See what a main panel upgrade costs.
  5. Check substituted equipment. If the panel or inverter changes, compare the warranties and spec sheets with the original.
  6. Read your contract’s change clause. Some contracts let you cancel without penalty if the price rises above a set amount or the design changes a lot.

Our page on what a solar contract should include explains why a clear change clause is worth asking for before you sign.

Change orders that should worry you

Most change orders are routine. Be more cautious when:

  • The change order arrives after work has started, with a request to sign so the crew can continue.
  • The price rises, but the explanation is vague (“site conditions”, “market changes”) with no detail.
  • Several small change orders add up to a large increase over the original price.
  • A lower-wattage or unnamed panel replaces the one in your contract, with no price reduction.
  • You’re told the original price can’t be honored unless you sign today.

If you aren’t comfortable, you can usually decline a change order. What happens next depends on your contract: the installer may proceed with the original design, propose another option, or the contract may allow either side to cancel. If a door-to-door sale is involved and you’re still within the FTC’s three-day cooling-off window, you can cancel the whole sale. Rules on home improvement contracts vary by state, so check your state briefing.

How to avoid surprises

You can cut down on change orders before you sign:

  • Ask whether the quote is based on an in-person site survey or on satellite images.
  • Ask the installer to check your electrical panel and roof condition before the contract, or to state in the quote what would happen if either needs work.
  • Ask for exact panel and inverter models in the contract, with a clause that substitutions must be equal or better and need your approval.
  • Ask for a cap on price changes, or a right to cancel if the price rises above a set amount.

These steps don’t guarantee a smooth project, but they turn most surprises into conversations rather than demands. Find more short answers on the Q&A floor.

A change order is a new agreement. You have the right to read it, question it and take time before signing, just as you did with the original contract.

When a change order tips the math

  • The system shrinks a lot but the price barely moves, raising the price per watt well above your other quotes.
  • A panel upgrade or roof repair adds enough cost to push payback past the time you expect to stay in the home.
  • Substituted equipment carries weaker warranties for the same price.

If a change order makes the project a worse deal than your next-best quote, it’s reasonable to ask whether you can cancel and go with another installer.

Key takeaways

  • A change order is a written change to your contract after signing.
  • They often follow the site survey: fewer panels fit, or the electrical panel needs work.
  • A fair one shows what changed, why, the new price and the new production estimate.
  • Recalculate price per watt and payback before you sign it.
  • Ask for a change clause in your contract before you sign the original.

Questions people also ask

Can an installer start work without my signed change order?

They shouldn’t. A change to price, size or equipment should be approved by you in writing before the work it covers begins. If a crew arrives and asks you to sign a change on the spot so they can keep going, it’s fair to ask them to pause until you’ve read it. Check your contract for how changes must be approved.

Is a change order a sign of a bad installer?

Not by itself. Many good installers issue change orders after the site survey because a satellite image can’t show everything, such as an old electrical panel or roof damage. What matters is how it’s handled: a clear reason, a fair price change, and time for you to decide. Repeated, vague or rushed change orders are the warning sign.

Can a change order lower my price?

Yes. If fewer panels fit or a planned item isn’t needed, the price should go down. Check that it falls in a reasonable proportion to the change. In the example on this page, the system shrank by 10% but the price fell by under 7%, which is worth asking about before you agree.

What if I don’t agree to a change order?

You can decline it. Your contract decides what happens next: the installer might build the original design, offer another option, or either side might be able to cancel. Ask the installer to explain your options in writing, and check whether any deposit is refundable if the project doesn’t go ahead.

Sources